Proposed timeline for projects

Bridgeport ISD community members vote on $185
million bond program to address facility needs.

May 2023

Begin Bridgeport Middle School renovation design

Fall 2023
  • Continue new elementary school design
  • Continue construction on Bridgeport Middle School renovation
Spring 2024
  • Begin new elementary school design
  • Begin construction on Bridgeport Middle School renovation
Winter 2024
  • Continue New elementary school design
  • Continue construction on Bridgeport Middle School renovation
Summer 2024
  • Begin High School auditorium design
  • Begin Bull Stadium renovation design
  • Begin field safety cover design
  • Begin softball & baseball facility renovation design
  • Begin tennis court renovation design
  • Begin new elementary school construction
  • Continue construction on BMS renovation
Fall 2024
  • Continue High School auditorium design
  • Continue Bull Stadium renovation design
  • Continue field safety cover design
  • Continue softball & baseball facility renovation design
  • Continue tennis court renovation design
  • Continue new elementary school construction
  • Continue construction on BMS renovation
Winter 2025
  • Continue High School auditorium design
  • Continue Bull Stadium renovation design
  • Continue field safety cover design
  • Continue softball & baseball facility renovation design
  • Continue new elementary school construction
  • Continue construction on BMS renovation
  • Begin tennis court renovation construction
Spring 2025
  • Complete BMS renovation
  • Complete tennis court renovation
  • Begin High School auditorium construction
  • Begin Bull Stadium renovation construction
  • Begin field safety cover construction
  • Begin softball & baseball facility renovation construction
  • Continue new elementary school construction
  • Continue construction on BMS renovation
Summer 2025
  • Continue High School auditorium construction
  • Continue Bull Stadium renovation construction
  • Continue field safety cover construction
  • Continue new elementary school construction
  • Continue softball & baseball facility renovation construction
Fall 2025
  • Complete softball & baseball facility renovation construction
  • Continue High School auditorium construction
  • Continue Bull Stadium renovation construction
  • Continue field safety cover construction
  • Continue new elementary school construction
Winter 2026
  • Complete new elementary school construction
  • Complete High School auditorium construction
  • Complete Bull Stadium renovation construction
  • Continue field safety cover construction
Spring 2026

Complete field safety cover construction

Summer 2026

NOTE: Factors, such as long periods of severe/inclement weather or unforeseen disruption of supply chains and availability of labor may impact the timeline.